Battery storage: decommissioning estimates

Home › Decommissioning › Battery storage

Insufficient data for a benchmark: 4 confirmed filings from 4 counties so far. They are listed below.

All statesFilingsCountiesTypical net costMiddle half
All states44Insufficient data

By state

StateFilingsCountiesTypical net costMiddle half
Massachusetts11Insufficient data
Minnesota33Insufficient data

Filings

ProjectStateCountyTypeSizeCost yearRemoval costSalvage creditNetNet per unitPrepared bySourceNot in the benchmark because
Andover BESS (New Leaf Energy)MassachusettsAndoverBattery storage · 20 MWh2025$232,531—$232,531$11,627/MWhNew Leaf Energyfiling
Snowshoe BESSMinnesotaOlmstedBattery storage150 MW · 600 MWh2024$902,415$400,830$501,584$836/MWhWestwoodfilingthe filing's per-MW net figure does not match its own totals
Midwater BESSMinnesotaFreebornBattery storage150 MW · 600 MWh2024$1,215,643$596,492$619,152$1,032/MWhWestwoodfiling
Crane Energy StorageMinnesotaOlmstedBattery storage200 MW · 800 MWh2024$15,047,608$1,154,200$13,893,408$17,367/MWhBurns & McDonnellfiling
North Star Energy StorageMinnesotaChisagoBattery storage80 MW · 320 MWh2025$5,600,000$16,300,000−$10,700,000−$33,438/MWh—filing
Shutler BESS (Oregon Trail Solar split)OregonGilliamBattery storage100 MW2026$217,356————filingno net figure

These are engineers' estimates written into filings with counties and state siting boards, not what decommissioning actually cost. Figures are net of the salvage credit the filing claims, in the dollars of the filing's cost year. Type, size and cost year are as filed. Unit costs are per MWac for solar, per MWh for battery storage and per turbine for wind.