Decommissioning: what the filings say it costs

Home › Decommissioning

143 decommissioning estimates for solar, battery storage and wind projects in 16 states, read from filings with counties and siting boards. Solar typically nets $35,648 per MWac after salvage (middle half $4,436 to $56,531, 54 filings in 43 counties).

TypeFilingsCountiesTypical net costMiddle half
Solar5443$35,648 $/MWac$4,436 to $56,531
Battery storage44Insufficient data
Wind1412$57,612 $/turbine$50,773 to $99,959

These are engineers' estimates written into filings with counties and state siting boards, not what decommissioning actually cost. Figures are net of the salvage credit the filing claims, in the dollars of the filing's cost year. A typical figure appears only when at least 8 confirmed filings from at least 3 counties; below that it reads Insufficient data and the filings are simply listed. Only filings we could re-read are counted: 72 meet the benchmark test, the rest are listed with the reason.

What stands out

  • The salvage credit decides the answer. 14 of the 72 benchmark filings show a negative net cost: the filing expects scrap and resale value to exceed removal cost, so on paper the project pays for its own removal.
  • Two engineers, one county, one year, very different answers. Two battery storage plans in Olmsted County, Minnesota (2024) put net cost at $836 and $17,367 a MWh, because one assumes the battery maker takes the batteries back at no cost.
  • Security often arrives late. Several Minnesota plans post financial security only from year 10 of operation, while the estimate shows net cost rising with the years.

By type

Try the Estimate Check Plans and prices

Source documents are public filings; each row links to its filing. Preparer firms are named, individual engineers never. Method: Methodology.