Decommissioning: what the filings say it costs
143 decommissioning estimates for solar, battery storage and wind projects in 16 states, read from filings with counties and siting boards. Solar typically nets $35,648 per MWac after salvage (middle half $4,436 to $56,531, 54 filings in 43 counties).
| Type | Filings | Counties | Typical net cost | Middle half |
|---|---|---|---|---|
| Solar | 54 | 43 | $35,648 $/MWac | $4,436 to $56,531 |
| Battery storage | 4 | 4 | Insufficient data | |
| Wind | 14 | 12 | $57,612 $/turbine | $50,773 to $99,959 |
What stands out
- The salvage credit decides the answer. 14 of the 72 benchmark filings show a negative net cost: the filing expects scrap and resale value to exceed removal cost, so on paper the project pays for its own removal.
- Two engineers, one county, one year, very different answers. Two battery storage plans in Olmsted County, Minnesota (2024) put net cost at $836 and $17,367 a MWh, because one assumes the battery maker takes the batteries back at no cost.
- Security often arrives late. Several Minnesota plans post financial security only from year 10 of operation, while the estimate shows net cost rising with the years.