| McLean County Wind Energy Center | Illinois | McLean | Wind | 248.2 MW100 turbines | 2017 | $13,239,950 | $7,959,000 | $5,280,950 | $52,810/turbine | Burns & McDonnell | filing | |
| Lee County wind | Illinois | Lee | Wind | 30 turbines | 2021 | — | — | $1,749,000 | $58,300/turbine | — | filing (Center for Rural Affairs wind guide, Table 1) | |
| Washington County wind | Maine | Washington | Wind | 13 turbines | 2022 | — | — | $739,999 | $56,923/turbine | — | filing (Center for Rural Affairs wind guide, Table 1) | |
| Isabella Wind Farm (Isabella Wind LLC) | MI | Isabella | Wind | 383.5 MW136 turbines | 2019 | $12,567,580 | — | $2,780,306 | $20,443/turbine | Mott MacDonald | Isabella County, Michigan: decommissioning plan, agreement and bond released under the Michigan FOIA, 2026-11-23 | |
| Plum Creek Wind Farm | Minnesota | Cottonwood/Murray/Redwood | Wind | 110 turbines | 2019 | $19,228,133 | $10,373,824 | $8,854,309 | $80,494/turbine | Geronimo Energy (developer, a National Grid company) | filing | |
| Buffalo Ridge Wind | Minnesota | Lincoln | Wind | 109 MW40 turbines | 2020 | $5,566,518 | $870,800 | $4,695,718 | $117,393/turbine | Atwell, LLC | filing | |
| Walleye Wind | Minnesota | Rock | Wind | 110.8 MW40 turbines | 2020 | $6,802,709 | $3,232,768 | $3,569,941 | $89,249/turbine | Tetra Tech, Inc. | filing | |
| Nobles County wind | Minnesota | Nobles | Wind | 134 turbines | 2021 | — | — | $38,264,370 | $285,555/turbine | — | filing (Center for Rural Affairs wind guide, Table 1) | duplicate of the primary filing for the same project |
| Nobles Wind Farm Repower (Xcel Energy) | Minnesota | Nobles/Murray | Wind | 134 turbines | 2021 | $47,119,748 | $8,815,111 | $38,304,638 | $285,856/turbine | Xcel Energy (Dismantling Cost Study) | filing | |
| Wheatridge Renewable Energy Facility East | Oregon | Morrow; Umatilla | Wind | 200 MW66 turbines | 2023 | $27,190,182 | — | — | — | — | filing | no net figure |
| Wheatridge Renewable Energy Facility Northeast | Oregon | Morrow; Umatilla | Wind | 37 turbines | 2026 | $11,300,000 | — | — | — | Tetra Tech | filing | no net figure |
| Dakota Range III Wind | South Dakota | Roberts and Grant | Wind | 151.2 MW36 turbines | 2018 | $11,214,900 | $9,306,900 | $1,908,000 | $53,000/turbine | DNV GL | filing | |
| Deuel Harvest North Wind Farm | South Dakota | Deuel | Wind | 300 MW112 turbines | 2018 | $11,149,300 | $7,893,000 | $3,256,300 | $29,074/turbine | Burns & McDonnell Engineering Company | filing | |
| Mitchell wind | South Dakota | — | Wind | 108 turbines | 2021 | — | — | $15,112,224 | $139,928/turbine | — | filing (Center for Rural Affairs wind guide, Table 1) | county not stated in the source (compilation table) |
| Brookings/Deuel wind | South Dakota | Brookings and Deuel | Wind | 105 turbines | 2021 | — | — | $10,870,545 | $103,529/turbine | — | filing (Center for Rural Affairs wind guide, Table 1) | |
| North Bend Wind | South Dakota | Hyde and Hughes | Wind | 200.2 MW71 turbines | 2021 | $11,459,950 | $7,903,300 | $3,556,650 | $50,094/turbine | Tetra Tech | filing | |
| Buffalo Ridge II Wind | South Dakota | Brookings and Deuel | Wind | 210 MW105 turbines | 2021 | $17,933,862 | $7,063,339 | $10,870,523 | $103,529/turbine | Barr Engineering Co. | filing | |
| South Deuel Wind | South Dakota | Deuel | Wind | 256.5 MW57 turbines | 2024 | $9,815,250 | $8,472,000 | $1,343,250 | $23,566/turbine | Burns & McDonnell Engineering Company | filing | |