Wind: decommissioning estimates

Home › Decommissioning › Wind

Typical net cost $57,612 $/turbine, middle half $50,773 to $99,959, across 14 filings in 12 counties, cost years 2017 to 2024.

All statesFilingsCountiesTypical net costMiddle half
All states1412$57,612 $/turbine$50,773 to $99,959

By state

StateFilingsCountiesTypical net costMiddle half
Illinois22Insufficient data
Maine11Insufficient data
MI11Insufficient data
Minnesota44Insufficient data
South Dakota64Insufficient data

Filings

ProjectStateCountyTypeSizeCost yearRemoval costSalvage creditNetNet per unitPrepared bySourceNot in the benchmark because
McLean County Wind Energy CenterIllinoisMcLeanWind248.2 MW100 turbines2017$13,239,950$7,959,000$5,280,950$52,810/turbineBurns & McDonnellfiling
Lee County windIllinoisLeeWind30 turbines2021——$1,749,000$58,300/turbine—filing (Center for Rural Affairs wind guide, Table 1)
Washington County windMaineWashingtonWind13 turbines2022——$739,999$56,923/turbine—filing (Center for Rural Affairs wind guide, Table 1)
Isabella Wind Farm (Isabella Wind LLC)MIIsabellaWind383.5 MW136 turbines2019$12,567,580—$2,780,306$20,443/turbineMott MacDonaldIsabella County, Michigan: decommissioning plan, agreement and bond released under the Michigan FOIA, 2026-11-23
Plum Creek Wind FarmMinnesotaCottonwood/Murray/RedwoodWind110 turbines2019$19,228,133$10,373,824$8,854,309$80,494/turbineGeronimo Energy (developer, a National Grid company)filing
Buffalo Ridge WindMinnesotaLincolnWind109 MW40 turbines2020$5,566,518$870,800$4,695,718$117,393/turbineAtwell, LLCfiling
Walleye WindMinnesotaRockWind110.8 MW40 turbines2020$6,802,709$3,232,768$3,569,941$89,249/turbineTetra Tech, Inc.filing
Nobles County windMinnesotaNoblesWind134 turbines2021——$38,264,370$285,555/turbine—filing (Center for Rural Affairs wind guide, Table 1)duplicate of the primary filing for the same project
Nobles Wind Farm Repower (Xcel Energy)MinnesotaNobles/MurrayWind134 turbines2021$47,119,748$8,815,111$38,304,638$285,856/turbineXcel Energy (Dismantling Cost Study)filing
Wheatridge Renewable Energy Facility EastOregonMorrow; UmatillaWind200 MW66 turbines2023$27,190,182————filingno net figure
Wheatridge Renewable Energy Facility NortheastOregonMorrow; UmatillaWind37 turbines2026$11,300,000———Tetra Techfilingno net figure
Dakota Range III WindSouth DakotaRoberts and GrantWind151.2 MW36 turbines2018$11,214,900$9,306,900$1,908,000$53,000/turbineDNV GLfiling
Deuel Harvest North Wind FarmSouth DakotaDeuelWind300 MW112 turbines2018$11,149,300$7,893,000$3,256,300$29,074/turbineBurns & McDonnell Engineering Companyfiling
Mitchell windSouth Dakota—Wind108 turbines2021——$15,112,224$139,928/turbine—filing (Center for Rural Affairs wind guide, Table 1)county not stated in the source (compilation table)
Brookings/Deuel windSouth DakotaBrookings and DeuelWind105 turbines2021——$10,870,545$103,529/turbine—filing (Center for Rural Affairs wind guide, Table 1)
North Bend WindSouth DakotaHyde and HughesWind200.2 MW71 turbines2021$11,459,950$7,903,300$3,556,650$50,094/turbineTetra Techfiling
Buffalo Ridge II WindSouth DakotaBrookings and DeuelWind210 MW105 turbines2021$17,933,862$7,063,339$10,870,523$103,529/turbineBarr Engineering Co.filing
South Deuel WindSouth DakotaDeuelWind256.5 MW57 turbines2024$9,815,250$8,472,000$1,343,250$23,566/turbineBurns & McDonnell Engineering Companyfiling

These are engineers' estimates written into filings with counties and state siting boards, not what decommissioning actually cost. Figures are net of the salvage credit the filing claims, in the dollars of the filing's cost year. Type, size and cost year are as filed. Unit costs are per MWac for solar, per MWh for battery storage and per turbine for wind.